September 13, 2011 05:00PM
Could you take a USB to the FMX unit and transfer data to USB. Create a new project in FW Office. After opening this new project, try the Read Job Data process. After data has been imported, do the yield numbers show large qtys as in the original project where the data had been synchronize through Connect Farm?

Thanks,

Kathy Cline,
Trimble Ag Software Support
For fast replies email: TABS_Support@trimble.com
SubjectAuthorPosted

Yield data is wrong when transfered through cellular connection

HendersonAgTechSeptember 13, 2011 09:33AM

Re: Yield data is wrong when transfered through cellular connection

Kathy ClineSeptember 13, 2011 05:00PM



Sorry, you do not have permission to post/reply in this forum.